Previous news items - 2006
- January 2007 - User training sessions commence for researchers and research administrators.
- January 2007 - IRISHelp@mq.edu.au operational.
- 13th December - Commence roll out of IRIS to Researchers and Research administrators.
- 23rd November - Project team complete the eight awareness/training sessions for IRIS web publications.
- 8th November - Everyone message sent with dates of awareness/training sessions.
- 6th November - ResearchMaster deliver the release of web software required for IRIS to be rolled out, allowing installation and testing to commence.
- 2nd October - IRIS live for back-office reporting of publications activity 2000-2005.
- 30th August - First successful load of 2000-2005 publications data into IRIS test system.
- 15th August - Systems administration and publications module training for project team complete.
- 7th August - Requirements specification for web pilot of internal grant schemes sent to ResearchMaster for development (MQNS and Safety Net).
- 27th July - First meeting of the IRIS Reference Group providing strategic guidance to the IRIS project team.
- 28th June - Project team start their training on the ResearchMaster product.
- 26th June - IRIS Steering Group approve Project Initiation Document, Project Scope, High Level Schedule and Communications Plan.
- 22nd June - ResearchMaster Enterprise software package is installed in the ITS data centre.
- 29th May - Contract signed with ResearchMaster for the supply of their Enterprise software package.
- 12th May - First meeting if the IRIS Project Steering Group.
- 3rd May - Realisation consultants appointed to document the ‘as is’ business processes in the HDRU and the Research Office.
- 1st May - Allyn Sayers, Semira Dautovic, Natalie Blaik and Ruth Shegog seconded full-time to the IRIS project.
- 28th April - Contract negotiations opened with preferred software supplier.
- 20th March 2006 - Mark Ellis appointed Project Manager of the IRIS project.
Previous news items - 2005
- 4th Decemeber - University Council approves IRIS Project budget.
- November - Needs analysis workshops and vendor presentations.
Senior Management Fortnightly Updates 2006
As of April 2007, the IRIS Project is not issuing updates on a fortnightly basis.